The SBC Cost Breakdown

Phase-by-phase capital cost, with all assumptions named. This memo provides the engineering view of the SBC programme capital cost — phase by phase, every assumption labelled. The first of three companion economic memos: this one costs the build, Memo 20 covers the return, Memo 21 the without-SBC counterfactual.

Memo19 — Cost Breakdown
AuthorBrett Murrell
Versionv1.0
Date20 May 2026
Design maturity10–15%
Words~7,200
Abstract

This memo sets out the indicative capital cost of the Sovereign Build Corporation (SBC) programme on a phase-by-phase basis, using locked unit rates from the MMC cost catalogue for the viaduct structure and clearly-labelled working estimates from the Phase 0 working document for the services that ride on it. Phase 0 — the Melbourne–Brisbane inland spine — is costed at $138–257 billion across 2,284 km. The seven Phase 0 spurs together add a further $203–381 billion across 3,310 km. Phase 1 adds the first two continental corridors at $147–241 billion. Phase 2 and Phase 3 complete the 23,200 km network at $98–164 billion each. Plus Alice Hub at $65–133 billion (PHES generation, MMC-VA trunk aqueduct from northern catchments, MMC-VD finger viaducts, pump stations — see Memo 5 §11 for the breakdown). Total gross programme capex: $750–1,340 billion at current unit rates, before volume-production reductions are fully applied. Every figure is at 10–15% design maturity — the same maturity at which the HSRA Stage 1 business case was submitted. Every assumption is labelled. This memo costs the build, nothing else. Revenue is the subject of Memo 20. Offsets against existing programmes are the subject of Memo 21.

23,200
km network total across 12 phases
$750–1,340B
Gross capex at current rates, 10–15% design maturity
~38%
Wright's Law reduction at volume (Phases 1–3)
$16.6B
Phase 0 viaduct structure (locked at MMC rates)

1. Purpose and methodology

This memo costs the SBC programme phase by phase. It does only that. It is the first of three companion economic memos:

The three together make the complete economic case. This memo provides the foundation that the other two reference.

1.1 Design-maturity stance

All figures in this memo are at 10–15% design maturity. This is the same design maturity at which the High Speed Rail Authority submitted its Stage 1 business case to Infrastructure Australia in December 2024. IA's evaluation of that case (November 2025) explicitly stated: "it is currently not possible to make a confident assessment of the proposal's benefit-cost ratio." The HSRA case did not, however, document its assumption set at this level of detail.

The methodology stance of this memo is the opposite. Transparent assumption documentation is not a weakness — it is the precondition for credibility. Every line item below is labelled with one of four confidence grades:

A consolidated assumption register sits at §9 of this memo, naming every assumption that materially affects the totals.

1.2 What this memo costs

The capex breakdown covers the physical SBC corridor build — the elevated multi-modal viaduct, the services that ride on it, the stations and interfaces, and the foundation civil works.

It does not cover:

Keeping these out of the capex memo prevents double-counting and keeps the corridor-build cost clearly visible.

2. Cost components and unit rates

Every kilometre of SBC corridor is the sum of four cost components: viaduct structure, services, install, and a per-corridor share of stations. Plus contingency on the lot.

2.1 Viaduct structure (LOCKED at MMC site rates)

The MMC cost catalogue at multimodalcorridors.com/costs.html publishes locked per-kilometre rates for each viaduct configuration:

Configuration Description $/km
MMC-VA Dual-leg, five-level, 50 m deck. Continental main artery. Carries freight rail, services, hyperloop reservation, maglev top deck, plus continental aqueduct as governing load case. $13.97 M/km
MMC-VB Dual-leg, two-level, freight at 6 m + maglev at 17 m + HVDC arms + gas/hydrogen/water/fibre services. The Phase 0 corridor workhorse. $7.27 M/km
MMC-VC Single-leg, single-deck, passenger maglev only. Used on Phase 0-2 and Phase 0-3 (passenger-priority corridors). $2.38 M/km
MMC-VD Single-leg, single-level finger viaduct, water + power + service rail + fibre. Used for water-capture spurs off MMC-VA main aqueduct. $2.11 M/km

Each of these rates is the sum of three layers: Structure (foundation, pylon, cap beams, deck, walkway), Services (the supports and brackets for what rides on the structure), and Install (field labour and plant). The detailed breakdown for each — material cost per module, install hours, plant rates — is on the MMC site cost pages.

Confidence: LOCKED at pre-feasibility grade, ±30%. Pre-feasibility means the engineering is sufficient to compare across designs and to size the programme. Detailed engineering and quantity surveying are required before any binding-grade cost estimate.

2.2 Services on the structure (WORKING ESTIMATES)

The MMC cost catalogue is in development for the services that ride on the viaduct structure. The per-km rates for track, maglev guideway, HVDC conductors, water pipes, fibre, and pumping are not yet locked at the MMC site. The MMC site states explicitly that each service-component cost page is "in development."

This memo therefore uses working estimates from the Phase 0 Working Document Article 28A assumption register. Each is labelled accordingly.

Service Working unit rate Basis
Freight rail track $1.0–1.5 M/km per track Inland Rail benchmark ~$18 M/km includes all civil; track-only component for electrified heavy freight at this rate.
Maglev guideway $15–30 M/km Global maglev benchmarks €30–70 M/km (2003 prices, inflation-adjusted to ~AUD $65–160 M/km). Working estimate assumes a technology-transfer deal achieves 50–70% cost reduction (Shanghai precedent — Chinese local manufacture vs German import). Highest uncertainty item in the programme.
HVDC transmission (conductors + insulators) $2–4 M/km AEMO ISP rates for HVDC conductor on dedicated towers, less the tower component (carried by the corridor).
HVDC converter terminals (per station) $1.0–1.5 B per terminal Public benchmark from European HVDC interconnector projects.
Branch water pipe (Phase 1+ corridor build) $1.5–3 M/km Working assumption. Detailed MMC engineering pending.
Continental aqueduct (Phase 1+ / VA corridors) $4–8 M/km Working assumption. Detailed MMC engineering pending. Larger conduit, higher pressure rating.
Pumping infrastructure Project-specific Lift-dependent. Allocated to Alice Hub PHES capex, not corridor capex.
Fibre and SCADA $0.3–0.6 M/km Standard fibre-optic corridor backbone with control systems.

Confidence: WORKING ESTIMATE. These rates are honest pre-feasibility working numbers. The MMC engineering work to lock them is in progress.

2.3 Stations (UNDER MMC SCOPING)

The Stations cost page on the MMC site is currently a stub ("in development"). Detailed station unit-rate engineering has not yet been completed.

For this memo, stations are costed on the following working assumption:

Station class $/station Examples
Major intermodal hub $400–800 M WSA, Brisbane, Melbourne, Newcastle, Adelaide, Perth — major freight + maglev + connecting interchange
Intermediate freight + passenger station $150–300 M Bendigo, Albury, Wagga, Bathurst, Dubbo, Tamworth, Toowoomba — multimodal stops on spine
Passenger-only station (MMC-VC corridors) $80–180 M Phase 0-2 and Phase 0-3 intermediate stops
Freight-only siding / intermodal interface $40–100 M Small spurs, mine sidings, port interfaces

Basis: working rates derived from comparable public infrastructure — Inland Rail intermodal hubs, Sydney Metro interchange stations, Brisbane Cross River Rail stations. Australian construction labour premium applied.

Confidence: UNDER MMC SCOPING. The per-station rates above are explicit working assumptions for this memo. Each station's actual scope (passenger volume, freight transfer capacity, intermodal connections) will vary and the detailed costing will follow from station-by-station design.

2.4 Contingency, escalation, and volume production

Three further line items apply at programme level:

3. Phase 0 — The spine

Route: Melbourne → Brisbane via the inland alignment. Distance: 2,284 km (provisional pending re-measure of the new inland-via-Bathurst/Dubbo alignment). Viaduct configuration: MMC-VB (dual-leg, two-level, full multi-service). Services carried: 3-track electrified freight + 2-track maglev passenger + HVDC arms + gas + hydrogen + water + fibre.

3.1 Phase 0 station list (LOCKED)

The Phase 0 spine stops at 18 stations from Melbourne to Brisbane:

Melbourne · Bendigo · Echuca · Shepparton · Benalla · Wangaratta · Albury · Wagga Wagga · Goulburn · Western Sydney Airport · Bathurst · Dubbo · Muswellbrook · Tamworth · Armidale · Warwick · Toowoomba · Brisbane.

Station classification for cost purposes:

3.2 Phase 0 cost breakdown

Item Quantity Unit rate Cost ($B) Confidence
Viaduct structure (MMC-VB) 2,284 km $7.27 M/km $16.6 B Locked (MMC site)
Freight rail track (3 tracks) 2,284 km × 3 $1.0–1.5 M/km $6.9–10.3 B Working estimate
Maglev guideway (2 tracks) 2,284 km × 2 $15–30 M/km $68.5–137.0 B Working estimate
HVDC transmission (conductors) 2,284 km $2–4 M/km $4.6–9.1 B Working estimate
HVDC converter terminals ~6 terminals along spine $1.0–1.5 B each $6.0–9.0 B Working estimate
Fibre + SCADA backbone 2,284 km $0.3–0.6 M/km $0.7–1.4 B Working estimate
Major intermodal hubs (5) 5 stations $400–800 M each $2.0–4.0 B Under MMC scoping
Intermediate stations (13) 13 stations $150–300 M each $2.0–3.9 B Under MMC scoping
Subtotal — Phase 0 pre-contingency $110.7–197.6 B
Contingency (25–30%) $27.7–59.3 B Standard for design maturity
TOTAL PHASE 0 (current rates) $138.4–257.0 B At 10–15% design maturity
Volume-production reduction (n/a Phase 0) Phase 0 is the proving build

Phase 0 indicative cost: $138 – $257 billion at current rates.

Phase 0 alone is the largest single capex line in the programme — because it is the proving build at current unit rates, before manufacturing scale brings down per-km costs for the continental phases. Subsequent phases benefit from the Wright's Law -38% volume production effect once 800,000 spans have been manufactured.

3.3 Reconciliation with the Phase 0 Working Document

The Phase 0 Working Document Article 27B states SBC Phase 0 cost ~$142 B current rates / ~$88 B volume production. This memo's figure of $138–257 B at current rates is consistent with the lower bound of that range but extends to a higher upper bound. The reason is that this memo applies the full upper-bound maglev guideway rate ($30 M/km × 2 tracks = $137 B for maglev guideway alone) which is the highest-uncertainty line item in the programme.

The two figures reconcile when read as follows:

The maglev guideway cost is the largest single uncertainty in the programme. The technology-transfer negotiation is identified as a critical-path action in the Phase 0 Working Document (Action A99).

4. Phase 0 spurs (0-1 through 0-7)

The seven Phase 0 spurs extend the spine to additional regional centres, ports, and capital cities. Each is costed separately using the same component build-up.

4.1 Phase 0-1 — Hunter Valley spur (113 km)

Route: Newcastle → Maitland → Singleton → Muswellbrook Configuration: MMC-VB multi-modal Stations (LOCKED): Newcastle, Maitland, Singleton, Muswellbrook (4)

Item Cost ($B)
Viaduct structure (MMC-VB) — 113 km × $7.27 M/km $0.82
Freight rail track (3 tracks) — 113 km × 3 × $1.0–1.5 M/km $0.34–0.51
Maglev guideway (2 tracks) — 113 km × 2 × $15–30 M/km $3.4–6.8
HVDC transmission — 113 km × $2–4 M/km $0.23–0.45
Branch water pipe — 113 km × $1.5–3.0 M/km $0.17–0.34
Fibre + SCADA — 113 km × $0.3–0.6 M/km $0.03–0.07
Stations: 1 major hub (Newcastle) + 3 intermediate $0.85–1.7
Subtotal $5.84–10.7 B
Contingency 25–30% $1.46–3.21 B
TOTAL Phase 0-1 $7.3 – $13.9 B

4.2 Phase 0-2 — Newcastle to Sydney Central (142 km)

Route: Newcastle → Watagans → Hornsby → Parramatta → Sydney Central Configuration: MMC-VC single-leg single-deck (passenger-only) Stations: Newcastle, Sydney Central confirmed; intermediates UNDER MMC SCOPING (assumed ~4–6 passenger-only stations along the 142 km).

Item Cost ($B)
Viaduct structure (MMC-VC) — 142 km × $2.38 M/km $0.34
Maglev guideway (2 tracks) — 142 km × 2 × $15–30 M/km $4.26–8.52
Fibre + SCADA — 142 km × $0.3–0.6 M/km $0.04–0.09
Stations: 2 major hub endpoints + ~4–6 passenger-only intermediate $1.12–2.68
Subtotal $5.76–11.63 B
Contingency 25–30% $1.44–3.49 B
TOTAL Phase 0-2 $7.2 – $15.1 B

Note: Phase 0-2 cost is dominated by maglev guideway (passenger-only spec). No freight track, no HVDC transmission backbone — these stay on the Phase 0 spine and the MMC-VB corridors. Water pipes are not part of the Phase 0 build at all — the continental water network arrives with Phase 1, 2, and 3 when Alice Hub and the central engine come online.

4.3 Phase 0-3 — WSA to Sydney Central (50 km)

Route: Western Sydney Airport → Parramatta → Sydney Central Configuration: MMC-VC single-leg single-deck (passenger-only) Stations: WSA, Parramatta, Sydney Central (3 confirmed). Likely 1–2 additional intermediate stations within urban Sydney UNDER MMC SCOPING.

Item Cost ($B)
Viaduct structure (MMC-VC) — 50 km × $2.38 M/km $0.12
Maglev guideway (2 tracks) — 50 km × 2 × $15–30 M/km $1.50–3.00
Fibre + SCADA — 50 km × $0.3–0.6 M/km $0.02–0.03
Stations: 3 major + ~1–2 intermediate $1.30–2.76
Subtotal $2.94–5.91 B
Contingency 25–30% $0.74–1.77 B
TOTAL Phase 0-3 $3.7 – $7.7 B

Note: Stations dominate the cost on this 50 km spur — three major-hub stations at the endpoints plus urban Sydney intermediate stops carry more cost than the viaduct itself.

4.4 Phase 0-4 — Toowoomba to Port Douglas (1,645 km)

Route: Toowoomba → Brisbane connection point → Bundaberg → Rockhampton → Mackay → Townsville → Cairns → Port Douglas Configuration: MMC-VB multi-modal Stations: Endpoints confirmed (Toowoomba on Phase 0 spine, Port Douglas terminus). Intermediate stations UNDER MMC SCOPING — assumed ~8–10 stations along the corridor at coastal QLD regional centres (Bundaberg, Gladstone, Rockhampton, Mackay, Bowen, Ayr, Townsville, Ingham, Innisfail, Cairns).

Item Cost ($B)
Viaduct structure (MMC-VB) — 1,645 km × $7.27 M/km $11.96
Freight rail track (3 tracks) $4.94–7.40
Maglev guideway (2 tracks) $49.4–98.7
HVDC transmission $3.29–6.58
HVDC converter terminals (~4) $4.0–6.0
Branch water pipe $2.47–4.94
Fibre + SCADA $0.49–0.99
Stations: 2 major hubs + ~8–10 intermediate $2.0–4.6
Subtotal $78.6–141.2 B
Contingency 25–30% $19.6–42.4 B
TOTAL Phase 0-4 $98.2 – $183.5 B

4.5 Phase 0-5 — Brisbane to Port Macquarie (447 km)

Route: Brisbane → Gold Coast → Tweed Heads → Byron Bay → Lismore → Grafton → Coffs Harbour → Kempsey → Port Macquarie Configuration: MMC-VB multi-modal Stations: Endpoints confirmed. Intermediate stations UNDER MMC SCOPING — assumed ~5–7 stations.

Item Cost ($B)
Viaduct structure (MMC-VB) — 447 km × $7.27 M/km $3.25
Freight rail track (3 tracks) $1.34–2.01
Maglev guideway (2 tracks) $13.4–26.8
HVDC transmission $0.89–1.79
HVDC converter terminals (~2) $2.0–3.0
Branch water pipe $0.67–1.34
Fibre + SCADA $0.13–0.27
Stations: 1 major + ~6 intermediate $1.30–2.6
Subtotal $22.98–41.06 B
Contingency 25–30% $5.74–12.32 B
TOTAL Phase 0-5 $28.7 – $53.4 B

4.6 Phase 0-6 — Melbourne to Adelaide (665 km)

Route: Melbourne → Ballarat → Horsham → Bordertown → Murray Bridge → Adelaide Configuration: MMC-VB multi-modal Stations: Endpoints confirmed. Intermediate stations UNDER MMC SCOPING — assumed ~4–6 stations.

Item Cost ($B)
Viaduct structure (MMC-VB) — 665 km × $7.27 M/km $4.83
Freight rail track (3 tracks) $2.00–3.00
Maglev guideway (2 tracks) $19.95–39.9
HVDC transmission $1.33–2.66
HVDC converter terminals (~3) $3.0–4.5
Branch water pipe $1.00–2.00
Fibre + SCADA $0.20–0.40
Stations: 2 major hubs + ~5 intermediate $1.55–3.10
Subtotal $33.86–60.39 B
Contingency 25–30% $8.47–18.12 B
TOTAL Phase 0-6 $42.3 – $78.5 B

4.7 Phase 0-7 — Canberra to Eden (250 km)

Route: Canberra → Cooma → Bombala → Eden Configuration: MMC-VB multi-modal (freight-priority spur to deepwater Pacific port) Stations: Endpoints confirmed (Canberra on spine, Eden terminus). Intermediates UNDER MMC SCOPING — assumed 2–3.

Item Cost ($B)
Viaduct structure (MMC-VB) — 250 km × $7.27 M/km $1.82
Freight rail track (3 tracks) $0.75–1.13
Maglev guideway (2 tracks) $7.5–15.0
HVDC transmission $0.50–1.00
HVDC converter terminals (~1) $1.0–1.5
Branch water pipe $0.38–0.75
Fibre + SCADA $0.08–0.15
Stations: 1 major (Eden port) + 2–3 intermediate $0.7–1.7
Subtotal $12.73–22.05 B
Contingency 25–30% $3.18–6.62 B
TOTAL Phase 0-7 $15.9 – $28.7 B

4.8 Phase 0 spurs total

Spur Distance Cost ($B)
Phase 0-1 Hunter Valley 113 km $7.3–13.9
Phase 0-2 Newcastle–Sydney 142 km $7.2–15.1
Phase 0-3 WSA–Sydney 50 km $3.7–7.7
Phase 0-4 Toowoomba–Port Douglas 1,645 km $98.2–183.5
Phase 0-5 Brisbane–Port Macquarie 447 km $28.7–53.4
Phase 0-6 Melbourne–Adelaide 665 km $42.3–78.5
Phase 0-7 Canberra–Eden 250 km $15.9–28.7
TOTAL Phase 0 spurs 3,310 km $203.3 – $380.8 B

Combined Phase 0 (spine + 7 spurs): 5,594 km, $341.7 – $637.8 B at current rates.

The Phase 0 spurs are heavily skewed by Phase 0-4 (Toowoomba–Port Douglas) — at 1,645 km it is more than half the total spur distance. The other six spurs sum to ~1,665 km and ~$105–197 B.

5. Phase 1 — First continental (6,775 km)

Routes:

Configuration: MMC-VA continental (Big Bertha, five-level dual-leg, 50 m deck) for the two main continental corridors carrying the transcontinental aqueduct. MMC-VB for the Perth–Albany spur.

Stations: Endpoints confirmed. Intermediates UNDER MMC SCOPING per corridor — assumed station counts based on regional centres along each route.

5.1 Phase 1 cost build-up

For Phase 1 onward, volume-production effects begin to apply. The Wright's Law -38% reduction reaches its full effect after ~800,000 spans manufactured. Phase 0 (5,594 km × ~40 pylons/km = ~224,000 pylons) represents ~28% of programme volume; Phase 1 brings the cumulative total past ~50% of the curve. For this memo, Phase 1 is costed at a working -15% reduction from current rates, with full volume effects applied to Phases 2 and 3.

Sub-phase Distance Configuration Cost ($B) at -15% volume
SBC #1 Brisbane–Perth 3,519 km MMC-VA continental $76.4–125.0
SBC #2 Darwin–Adelaide 2,661 km MMC-VA continental $57.8–94.6
Phase 1-1 Perth–Albany 595 km MMC-VB multi-modal $12.9–21.2
TOTAL Phase 1 (at -15%) 6,775 km $147.0 – $240.8 B

Note on MMC-VA vs MMC-VB cost effect: MMC-VA at $13.97 M/km is approximately double MMC-VB at $7.27 M/km — but it carries the full continental aqueduct (Design A 15.2 m × 9.6 m conduit) which the working doc identifies as delivering ~11,460 GL/yr per corridor. The cost premium is the price of the continental water transfer that makes the centre productive.

Alice Hub allocation: $65–133 B (see Memo 5 §11 for the breakdown) is most naturally allocated to Phase 1 since SBC #2 passes through Alice Springs and the head pond infrastructure and trunk aqueduct alignment follows the SBC #2 corridor build. Alice Hub is excluded from the corridor capex above but added at the programme level — see §7.

6. Phase 2 and Phase 3 — Network closure

6.1 Phase 2 — Northern corridors (5,416 km)

Routes:

Configuration: MMC-VA continental for both (carrying continental aqueduct extensions).

By Phase 2 the manufacturing scale has reached full volume — Wright's Law -38% reduction applies.

Sub-phase Distance $/km at volume (MMC-VA: $13.97 × 0.62 = $8.66 M/km) Cost ($B)
SBC #3 Albury–Karumba 2,238 km $8.66 M/km × 2,238 km + services + stations + contingency $40.6–67.7
SBC #4 Mackay–Port Hedland 3,178 km Same build-up $57.7–96.1
TOTAL Phase 2 (at -38%) 5,416 km $98.3 – $163.8 B

6.2 Phase 3 — Network closure (5,413 km)

Routes:

Configuration: MMC-VA continental.

Sub-phase Distance Cost ($B) at -38% volume
SBC #5 Derby–Esperance 1,871 km $34.0–56.6
SBC #6 Albany–Port Douglas 3,542 km $64.4–107.2
TOTAL Phase 3 (at -38%) 5,413 km $98.4 – $163.8 B

7. Programme rollup

Bringing every phase together:

Phase Distance Cost ($B) Note
Phase 0 spine 2,284 km $138.4–257.0 Current rates (proving build)
Phase 0 spurs (7 spurs, 0-1 through 0-7) 3,310 km $203.3–380.8 Current rates
Phase 1 (SBC #1, SBC #2, 1-1) 6,775 km $147.0–240.8 At -15% volume reduction
Phase 2 (SBC #3, SBC #4) 5,416 km $98.3–163.8 At -38% volume reduction
Phase 3 (SBC #5, SBC #6) 5,413 km $98.4–163.8 At -38% volume reduction
Subtotal — SBC corridor capex 23,198 km $685.4 – $1,206.2 B
Plus: Alice Hub n/a $65 – 133 B See Memo 5 §11 for breakdown
TOTAL SBC PROGRAMME CAPEX 23,198 km $750 – $1,340 B At 10–15% design maturity

7.1 Phasing — when each phase happens

Phase Year (indicative) Distance Note
Phase 0.1 (Hunter spur + Phase 0 first sections) 2027–2030 ~434 km first wave First revenue Month 20
Phase 0 spine completion 2030–2034 2,284 km Eastern spine operational
Phase 0 spurs (0-2, 0-3 priority) 2031–2035 192 km passenger Sydney connections live
Phase 0 spurs (0-1, 0-5, 0-6, 0-7) 2032–2037 1,475 km Coast + Adelaide connections
Phase 0-4 (Toowoomba–Port Douglas) 2035–2042 1,645 km Long QLD coastal spur
Phase 1 (SBC #1, #2, 1-1) 2034–2042 6,775 km First continental
Phase 2 (SBC #3, #4) 2040–2048 5,416 km Northern corridors
Phase 3 (SBC #5, #6) 2044–2050 5,413 km Network closure

The phases overlap. SBC #1 (Brisbane–Perth) can begin construction while Phase 0 spurs are still completing, because manufacturing capacity and crew availability scale across phases. This is part of why the gross capex figure is misleading on its own — it's a 20+ year programme, not a single-decision-now spend.

8. The honest qualifications

This memo is at 10–15% design maturity. Reading it as anything else would be a misrepresentation. The qualifications below sit at the front of any conversation about these numbers.

8.1 Maglev guideway is the dominant uncertainty

Maglev guideway accounts for $135–230 B of the gross programme capex at the upper bound — the single largest line item. The technology-transfer negotiation that brings this rate down from international ($65–160 M/km) to working ($15–30 M/km) is the highest-leverage commercial action in the programme. Without it, the upper-bound figures hold; with it, the lower-bound figures hold.

8.2 Stations are mostly under MMC scoping

Of the ~95 stations across the full network, only the Phase 0 spine list (18) and Phase 0-1 list (4) are locked. The remaining ~73 stations are working assumptions. Per-station rates are also working assumptions until the MMC Stations cost page completes. Station cost uncertainty is the second-largest line-item uncertainty after maglev guideway.

8.3 Continental water conduit (Aqueduct VA) cost is a working estimate

The MMC site Aqueduct VA cost page is in development. The $4–8 M/km working rate used in this memo is honest at pre-feasibility level but the MMC engineering work to lock the figure is pending.

8.4 Phase 0 distance is provisional

The Phase 0 spine distance is stated as 2,284 km pending re-measurement of the new inland-via-Bathurst/Dubbo alignment. Three earlier figures (2,290 / 2,401 / 2,423 km) exist in older documents. The corridor distance is a structural input to every cost line on Phase 0 — a ±5% re-measure changes the Phase 0 total by ±$7–13 B.

8.5 Foundation depth varies

All foundation costs above are at the MMC catalogue baseline depth (15 m for MMC-VB, 20 m for MMC-VA, 10 m for MMC-VC and VD). Real foundation depths will vary with geology — river crossings, floodplain sections, escarpment crossings will require deeper foundations and proportionally higher cost. The Blue Mountains escarpment crossing in Phase 0 (working doc Article 26) carries a $180–540 M premium across ~15 km that is allocated to the contingency line above rather than the structural line.

8.6 Currency, escalation, and discount rate

All figures are 2026 AUD nominal. Real-terms escalation across a 15–20 year build is not applied — for comparative analysis vs HSRA, vs the nuclear pathway, vs AEMO ISP transmission, the comparison is more honest in constant 2026 dollars. Memo 20 (revenue) will apply NPV discounting consistent with infrastructure-financing convention. Memo 21 (counterfactual) will use the same conventions for the alternative programmes.

9. Consolidated assumption register

Every assumption that materially affects the programme totals, in one register.

9.1 Distance assumptions

Assumption Value Confidence Sensitivity
Phase 0 spine distance 2,284 km Provisional pending re-measure ±5% = ±$7–13 B on Phase 0
Phase 0-1 to 0-7 spur distances Per route pages Locked Stable
Phase 1/2/3 corridor distances Per route pages Locked Stable
Network total 23,200 km Locked across all docs Stable

9.2 Unit-rate assumptions (viaduct structure)

Assumption Value Confidence Sensitivity
MMC-VA $/km $13.97 M/km LOCKED (MMC catalogue) ±30% pre-feasibility
MMC-VB $/km $7.27 M/km LOCKED (MMC catalogue) ±30% pre-feasibility
MMC-VC $/km $2.38 M/km LOCKED (MMC catalogue) ±30% pre-feasibility
MMC-VD $/km $2.11 M/km LOCKED (MMC catalogue) ±30% pre-feasibility

9.3 Unit-rate assumptions (services)

Assumption Value Confidence Sensitivity
Freight rail track $1.0–1.5 M/km per track Working estimate ±30% absorbed in contingency
Maglev guideway $15–30 M/km per track Working estimate (HIGHEST uncertainty) Could rise to $65–160 M/km without tech transfer
HVDC transmission conductor $2–4 M/km Working estimate ±30%
HVDC converter terminal $1.0–1.5 B per terminal Working estimate ±25%
Branch water pipe (VB corridors) $1.5–3.0 M/km Working estimate ±35%
Continental aqueduct (VA corridors) $4–8 M/km Working estimate (UNDER MMC SCOPING) ±40% — MMC engineering pending
Fibre + SCADA backbone $0.3–0.6 M/km Working estimate ±25%

9.4 Station assumptions

Assumption Value Confidence Sensitivity
Major intermodal hub $400–800 M each UNDER MMC SCOPING ±50% — MMC engineering pending
Intermediate freight + passenger station $150–300 M each UNDER MMC SCOPING ±50%
Passenger-only station (MMC-VC) $80–180 M each UNDER MMC SCOPING ±50%
Freight-only / intermodal interface $40–100 M each UNDER MMC SCOPING ±50%
Phase 0 spine station count 18 LOCKED Stable
Phase 0-1 spur station count 4 LOCKED Stable
Other spur station counts Working assumptions per spur UNDER MMC SCOPING ±2 stations per spur

9.5 Programme-level assumptions

Assumption Value Confidence Sensitivity
Contingency rate 25–30% Standard AACE Class 4 If 50% (HS2 level): Phase 0 rises by additional ~$23–58 B
Volume production reduction (Phase 1) -15% Working assumption ±10% applied effect
Volume production reduction (Phase 2, 3) -38% (full Wright's Law) Working assumption from MMC Megafactory model ±10% applied effect
Escalation Not applied (real 2026 AUD) Methodology choice Real-terms comparison stable
Design maturity 10–15% Same as HSRA business case All figures pre-feasibility

9.6 Excluded from this memo

Excluded item Where it sits Reason
Alice Hub $65–133 B, added at programme level (§7). See Memo 5 §11 for breakdown Separately costed system
Desert PV generation Memo 20 (revenue side) Industry-funded via PPAs
Sovereign manufacturing setup Memo 20 Industry-funded under sovereign-content mandate
AUKUS-repositioned defence allocation Memo 18 / 3% GDP envelope Separate funding envelope
O&M (operations and maintenance) Memo 20 Operating cost, not capex
Land acquisition TBD by detailed alignment Largely zero on existing rail easements; some on Phase 0 inland sections

10. What comes next

Memo 20 — The SBC Return on Investment will cover:

Memo 21 — Without the SBC will cover:

The three memos together make the complete economic case.

11. Bottom line

The SBC programme costs approximately $750 billion to $1,340 billion gross at current unit rates, at 10–15% design maturity, over a 20+ year build, across 23,200 km of continental network and the Alice Hub continental water-and-energy engine.

The lower bound assumes the maglev technology-transfer deal succeeds and the build benefits from volume-production rates on Phases 1, 2, and 3. The upper bound assumes neither.

This memo provides the engineering cost view — the corridor build, allocated phase by phase, plus the Alice Hub system (referenced to Memo 5 §11), every assumption named. It does not address revenue, offsets, or counterfactuals — those are the subjects of Memos 20 and 21.