Solar Sizing for the SBC: Reaching 1,000 GW

The arithmetic of the resource, the deployment footprint, and the power output. Why 1,000 gigawatts is not a stretch goal — it is what fits comfortably inside the four central Australian Solar Regions, with room to scale further as Asian demand grows.

Memo1 — Energy
AuthorBrett Murrell
Versionv1.0
Date10 May 2026
SeriesMMA Memos
Word count~3,500
The SBC programme has identified four contiguous Solar Regions in central Australia totalling 1,545,201 square kilometres — about 20% of Australia’s land area. The programme target is 1,000 gigawatts of installed solar capacity to power Australia and to export to Asia. At modern utility-scale solar density, 1,000 GW occupies approximately 40,000 km² — about 2.6% of the available regional area. At the central Australian solar resource, 1,000 GW produces about 2,100 terawatt-hours of clean electricity per year — eight times Australia’s current total electricity demand. The remaining 97% of the regional area stays available for indigenous land use, agrivoltaic productive country, grazing, and ecological reserve. And as Asian demand grows — driven by industrialisation, electrification, and the explosive growth of data centre and AI compute load — the programme can scale further. The land is not the constraint. The decisions to build the corridors, the cables, and the country are.
1.5M km²Solar Region area available
1,000 GWProgramme target installed
2.6%Of regions actually used
~2,100 TWhAnnual energy output
The four Solar Regions overlaid on Australia, with SBC corridors visible
The four Solar Regions overlaid on the SBC corridor network — central Australian solar zone, all four regions combined. ~1.5 million km² total.

1. What This Memo Does

The Sovereign Build Corporation (SBC) programme rests on a claim that needs to be demonstrated to anyone — partners, funders, journalists, members of the public — encountering it for the first time. The claim is that Australia can power itself and become one of the world’s major clean energy exporters from a fraction of the central Australian desert.

This memo does the arithmetic behind that claim. It works through how big the available solar resource actually is, how much land 1,000 gigawatts of installed solar actually occupies, how much electricity that actually produces, what the addressable Asian export market actually looks like, and how the programme is engineered to scale further as demand grows.

The numbers in this memo are pre-feasibility — within roughly ±20-30% of detailed engineering values. That is appropriate for a programme being publicly proposed and seeking partner engagement. The order of magnitude — that 1,000 GW occupies a small fraction of the resource and produces multiples of Australian domestic demand — is robust to reasonable variation in any single assumption.

The headline finding: the four Solar Regions could host the full 1,000 GW deployment on approximately 2.6% of their combined area. The remaining 97% stays available for other uses. And the programme can scale meaningfully above 1,000 GW if Asian demand justifies the build, while still occupying less than 5% of the available zone. Land is not the constraint on the SBC. The constraint is the decisions to build it.

2. The Solar Resource

2.1 Why central Australia is exceptional

Australia’s inland solar resource is the largest of any inhabited continent. Three measures of solar resource quality matter for utility-scale deployment: peak sun hours per day, capacity factor, and seasonal variation.

2.2 The four Solar Regions

The SBC programme has identified four contiguous Solar Regions in central Australia where solar deployment is most viable, accessible, and corridor-compatible:

RegionArea (km²)Approximate location
Solar Region 189,339Central NT, north of Alice Springs
Solar Region 2702,797Northwestern NT and eastern WA — the Tanami / Great Sandy Desert zone
Solar Region 3292,516South-central — northwest SA into WA, the Great Victoria Desert
Solar Region 4460,549Western, north WA into northwest NT
Total1,545,201About 20% of Australia’s land area
Solar Region 1 polygon, centred north of Alice Springs
Solar Region 189,339 km² · perimeter 1,542 km
Solar Region 2 polygon, Tanami and Great Sandy Desert zone
Solar Region 2702,797 km² · perimeter 3,696 km
Solar Region 3 polygon, Great Victoria Desert
Solar Region 3292,516 km² · perimeter 2,912 km
Solar Region 4 polygon, north WA into northwest NT
Solar Region 4460,549 km² · perimeter 2,753 km

For scale: 1,545,201 km² is approximately the size of Iran, twice the size of Texas, or six times the size of the United Kingdom. The combined area of the four Solar Regions is larger than 165 of the 195 countries on Earth.

3. The Land Footprint at 1,000 GW

3.1 Modern solar density

Modern utility-scale single-axis-tracking solar farms deliver approximately 40 to 60 MW of installed capacity per square kilometre, accounting for panel area, inter-row spacing, access roads, and equipment pads. The high end of the range applies to flat sites with good orientation and modern bifacial panels — the conditions central Australia overwhelmingly delivers.

The planning assumption used in this memo is 50 MW per km² — the mid-range modern value. At this density, 1,000 GW of installed solar requires:

1,000,000 MW ÷ 50 MW/km² = 20,000 km² of installed solar land

3.2 Real-world deployment area

The 20,000 km² figure is the theoretical floor. The realistic deployment area is somewhat larger because not all selected land is panel-suitable:

A realistic working assumption is that effective deployment area is 1.5 to 2 times the theoretical panel footprint. At 2 times the floor, 1,000 GW occupies approximately 40,000 km² — the figure used in the SBC Consortium Prospectus and consistent with deployment patterns observed in operational utility-scale solar at scale globally.

3.3 The headline number: 2.6%

40,000 km² of deployment across the four Solar Regions totalling 1,545,201 km²:

40,000 ÷ 1,545,201 = 2.59% — about 2.6%

The remaining 97.4% of the Solar Region area stays available for other uses. This is the headline of the Solar Regions argument: the SBC programme does not industrialise central Australia. It uses a small fraction.

3.4 What this looks like compared to known places

ComparisonArea (km²)
1,000 GW SBC footprint~40,000
Tasmania68,401
Simpson Desert176,000
Tanami Desert184,000
Great Victoria Desert348,750
Solar Region 1 alone (the smallest of the four)89,339

The 1,000 GW installation fits comfortably inside the Simpson Desert with room to spare. It occupies less than half of Solar Region 1, the smallest of the four. The four Solar Regions combined are nearly forty times the area required.

Land is not the constraint. Vision is.

4. The Power Output at 1,000 GW

4.1 Annual energy production

Annual energy output from installed solar capacity is the product of three quantities: installed capacity (in megawatts), hours in a year (8,760), and capacity factor (22–26% for the central Australian resource).

Capacity factorSourceAnnual output (TWh/yr)
22%Conservative — fixed tilt, average maintenance1,927
24%Mid-range planning — single-axis tracking2,102
26%Aggressive — single-axis bifacial, optimal maintenance2,277

The planning assumption is the mid-range figure: approximately 2,100 TWh per year at 1,000 GW installed.

4.2 What that means for Australia

Australia’s total electricity consumption (all sources, all sectors) in 2024 was approximately 265 TWh per year. The 1,000 GW SBC programme produces:

2,100 TWh ÷ 265 TWh = about 7.9 times Australia’s current total electricity demand

Even if Australian electricity demand grows substantially through electrification of transport, heating, and heavy industry — a plausible scenario seeing demand rise to 500 TWh/yr by 2050 — the 1,000 GW programme still produces approximately 4.2 times the projected 2050 domestic demand.

This is the basis for the SBC 50/50 split: 500 GW for Australia (powering the electrified domestic economy with substantial headroom for hydrogen and ammonia production, AI compute, desalination, heavy industry, and corridor town demand) and 500 GW for export.

4.3 The Asian export market

The eight major Asian electricity markets reachable by HVDC submarine cable from Australia have a combined demand of approximately 293 GW average and approximately 2,575 TWh per year. These markets are:

MarketAverage demand (GW)Annual demand (TWh/yr)
Singapore6.355
Indonesia35305
Malaysia22195
Thailand27235
Vietnam32280
Philippines14125
Japan110970
South Korea47410
Combined (today)2932,575

The 500 GW export portion of the SBC programme produces approximately 1,050 TWh per year — about 41% of the combined annual demand of those eight markets at today’s levels. Real market share at maturity will be meaningfully smaller than 41% — those countries also have their own domestic generation, other suppliers compete, and submarine cable losses reduce delivered energy. But the resource is sized correctly: the SBC export programme is bounded by transmission build-out and market access negotiations, not by Australian sun.

And critically — the 2,575 TWh/yr figure is today. Tomorrow’s number is much larger.

5. Demand is Rising — The Programme Scales

5.1 Asian demand is growing fast

Southeast Asian electricity demand has been growing at roughly 5–7% per year for two decades and is projected to continue at similar rates through 2050. The IEA’s mid-case projections show Southeast Asian electricity demand approximately doubling between 2024 and 2050. Indonesia alone — currently 305 TWh/yr — is projected to reach approximately 1,300 TWh/yr by 2050 in mid-case industrialisation scenarios. That single country’s growth in absolute demand exceeds Australia’s entire current consumption.

By 2050, the eight markets reachable from Australia could plausibly demand 4,500–5,000 TWh per year — nearly double today’s figure. The same 500 GW export from the SBC would represent only 21–23% of the 2050 market — a meaningful share, but well within commercially achievable territory if the export build-out keeps pace with demand growth.

5.2 Data centres and AI are the wild card

Global data centre electricity consumption is approximately 460 TWh per year today and is on a doubling trajectory. The IEA’s 2024 reporting projects global data centre demand could reach 1,000+ TWh per year by 2030 if AI compute growth continues at observed rates. By 2050, data centre demand alone could exceed 3,000 TWh per year globally — equivalent to today’s entire combined Asian electricity consumption.

This is a different kind of demand than residential or industrial growth. Data centres need cheap, abundant, clean, and continuous electricity. They will locate where electricity meets all four conditions. Australian central desert solar — with the world’s best irradiance, low seasonal variation, and an integrated programme of corridor-borne transmission and pumped-hydro firming via the Alice Hub — is one of a small number of places on Earth that can meet all four at scale.

Australia faces a strategic choice. Either the data centres and AI compute load locate offshore (in markets with weaker electricity economics but better incumbent infrastructure) and Australia exports raw electricity to feed them — or the data centres and AI compute locate in Australia, alongside the corridors and the solar fields, and Australia exports compute services rather than raw electricity. Both paths use the same generation. The difference is whether the high-margin downstream economy is captured here or elsewhere.

5.3 What expansion above 1,000 GW looks like

The SBC corridor architecture is engineered for expansion. Six SBC corridors — each carrying integrated transmission, water, gas, fibre, and transport — provide the backbone. The transmission component of each corridor is designed in stages: a base deployment that delivers Phase 1 export capacity, with the easements, foundations, and substations sized for future upgrade as demand justifies additional circuits. The corridor design standard accommodates approximately 100 GW per corridor at full upgrade. Across six corridors, that is 600 GW of corridor transmission — supplemented by additional generation zones connected by shorter spurs.

The 1,000 GW programme target is what the corridor architecture supports comfortably with current technology and current market sizing. Expansion above 1,000 GW is engineered as a possibility, not a commitment. Three pathways:

At 1,500 GW — a 50% expansion — the deployment footprint becomes approximately 60,000 km², or about 3.9% of the four Solar Regions. At 2,000 GW — doubling the current target — the footprint is approximately 80,000 km², about 5.2% of the regions. Even at double the programme target, 95% of the Solar Region area stays available for other uses.

Programme sizeAnnual output (TWh/yr at 24% CF)Footprint (km²)% of Solar Regions
500 GW (Phase 1 milestone)~1,050~20,0001.3%
1,000 GW (current target)~2,100~40,0002.6%
1,500 GW (expansion scenario)~3,150~60,0003.9%
2,000 GW (long-term ceiling)~4,200~80,0005.2%
The honest framing: the SBC programme is sized for 1,000 GW because that is what the corridor build-out, the cable manufacturing capacity, the financing architecture, and the demand-side commitments support over the next two decades. It is not the maximum the resource supports. As Asian demand grows, as data centres seek clean power at scale, and as electrification continues, the programme can scale further. The land doesn’t constrain that. The build doesn’t constrain that. Only the decision to scale it does.

6. Why This Memo Stops Here

This memo is deliberately scoped to the solar sizing question. It establishes:

It does not address — and these are deliberately left for separate memos — the agrivoltaic productive land use case for the unused 97% of the regions; the corridor town settlement architecture at 100 km spacing; the Alice Hub aqueduct and water systems that make the regions habitable and the panels maintainable; the indigenous partnership framework as foundation rather than afterthought; the financing architecture; the manufacturing programme behind the panels; and the submarine cable engineering.

The reason for the narrow scope: the solar sizing arithmetic is the first claim that gets challenged when the SBC programme is presented to anyone new. “You’re going to power Australia and Asia? From the desert? On how much land?” This memo answers that question with the numbers and the workings, and lets every other memo stand on the foundation that the resource is genuinely there.

7. Assumptions and Caveats

AssumptionValueConfidenceNotes
Modern PV installed density50 MW/km²HighIndustry standard for utility-scale single-axis tracking
Effective deployment multiplier2× theoretical floorMedium-HighAccounts for buffers, easements, exclusions
Australian central capacity factor24% mid-rangeHighMultiple Australian operational PV plants validate this range
Solar Region areas1,545,201 km² totalHighPolygon measurements verified against the SBC corridor route plan
Hours in a year8,760High
Australian electricity demand 2024265 TWh/yrHighAEMO and AEMC published data
Asian market combined demand today~2,575 TWh/yrMediumIEA / IRENA data; varies year to year
Asian demand 2050 mid-case~5,000 TWh/yrMedium-LowIEA mid-case projection; significant uncertainty
Data centre demand 2050~3,000+ TWh/yr globallyLow-MediumIEA projection; AI compute trajectory adds uncertainty
1,000 GW programme targetLockedLockedSBC Consortium Prospectus, Chapter 3.3
Per-corridor transmission ceiling~100 GW at full upgradeMedium-HighEngineering ceiling on six-corridor architecture

The figures in this memo are pre-feasibility — within approximately ±20-30% of detailed engineering values. Detailed engineering studies are required before the programme moves into binding commitment. The order of magnitude — that 1,000 GW occupies a small fraction of the available central Australian solar resource and produces multiples of Australian domestic demand — is robust to reasonable variation in any single assumption.

8. Next Steps